Foryd Harbour Public Realm

CEEQUAL Excellent (84.0%) – Whole Project Award
Version 4, May 2014 | Denbigshire, Wales

ClientDenbighshire County Council, Rhyl Harbour Board
DesignerDCC, Major Projects Group
ContractorsDawnus Construction Ltd
Assessor: Brendan Kemp and Joe Martin

Project Summary

In the Spring of 2012, a construction project to transform Rhyl broke ground, with the goal of increasing tourism and boosting the local economy. Another key goal of the project was to provide a safer, more scenic route for pedestrians and cyclists as part of the Wales Coast Path which follows the entire coastline of Wales.

The Rhyl Harbour project formed part of a stream that included a sustainable transport bridge, coastal erosion and flood protection works, harbour enhancements and the landscaping of the local areas. The contract was awarded to Dawnus Construction and the project management of the scheme was undertaken by Denbighshire County Council with an in-house design team undertaking the design of various elements of work, supplemented at various stages by external consultants.

Foryd Harbour Public Realm | CEEQUAL
The third phase of the scheme began in 2012 and included the construction of a 180m extended quay wall, a new public square and deepened harbour channel to improve navigation.

Challenges and Achievements

Physical Resources – Use and Management

After exploring various walling materials that would match the visual scale and structural requirements needed, it was decided that CPM’s Redi-Rock™ walling would be used because of the resulting visual impact it would have and because of the cost incentives that the Redi-Rock positive connection walling offers. The one tonne blocks of 1070mm long, 457mm high and 710mm deep incorporated a Miragrid 10 XT, 20 XT and 24 XT geogrid reinforced earth system. Conventional solutions such as cladded sheet piles were considered, though the cost of sheet piles and the associated cladding made the scheme unviable.

The use of Redi-Rock™ walling allowed the contractor to install approximately 50 blocks over a tidal cycle, with the whole construction of the 188m long, up to 7.5m high quay wall being undertaken in just 30 weeks. Following close monitoring of the finished wall and backfill there has been no settlement and the Redi-Rock™ wall has withstood significant wave action during the recent storms and achieves the required design expectancy as well as looking good. The scheme has ended up being a flagship scheme for the regeneration of Rhyl and has met all targets set.

The wall comprises:

  • Sheet piles at the toe to prevent erosion
  • Concrete foundations with mesh reinforcement
  • Redi-rock positive connection blocks – over 5300 blocks placed
  • Incorporating miragrid geogrids
  • Granular backfill

 

Technology:

  • Incorporates mass retaining wall design with reinforced earth designed
  • It has been used in America by using American design codes
  • First time used in the UK

 

Earthworks:

  • 55,000m³ of material excavated
  • 17,000m³ of material reused for reinforced earth backfill
  • 14,000m³ of material reused as general fill to public square
  • 24,000m³ of material reused to create additional and replenish sand dune system

Ecology and Biodiversity

The project took place in a diverse ecological environment on the estuary of the River Clwyd. It involved the replenishment and extension of the sand dune system at Horton’s Nose habituated by Common Lizards; protected in the UK under the Wildlife and Countryside Act 1981, and classified as a Priority Species in the UK Biodiversity Action Plan. All sand to create the dunes was reclaimed from the bed of the Estuary. Once the profile of the dunes was created, they were set in place with jute matting and marram grass, which not only created additional habitat for the lizards but also mitigated against dust creation and dune erosion.

During the construction phase, the dune system also became home to nesting Little Terns, on the Amber conservation list due to their vulnerable coastal nesting sites. The closure of an area of the beach to the public during the construction phase period and the general good maintenance of the area was thought to have attracted these rare, delicate seabirds. All works were programmed to avoid the nesting season and temporary works involved methods that protected the water environment. This construction included a sand/ silt bund for the extended quay wall and a land jetty wasused to enable construction of the bridge central caisson without disruption from plant or pollution.

People and Communities

Comprehensive community consultation took place on this project and meetings were held regularly with various harbour user groups. Local Councillors and Welsh Government ministers were regular visitors to the site. A very positive relationship was enjoyed and maintained with the only near neighbour of the project, Sunnyvale Caravan Park, who hosted the opening ceremony. Volunteers were used to work on the Dune System, erecting Newt fencing preconstruction and planting Marram Grass. A manned visitors centre was offered adjacent to the site compound in partnership with the Harbour Master’s Office throughout the construction phase, and displays were located in local commercial centres. The bridge was named through a competition for local school children and a local primary school was also given a tour of the site. Other benefits included jobs for two local operatives during the construction phase, a youth unemployment scheme, and local harbour users employed for safety boat operations. No complaints were received during the construction process and Dawnus consistently scored highly is Considerate Constructors Assesments.

Foryd Harbour Public Realm | CEEQUAL

Foryd Harbour Public Realm | CEEQUAL

To what extent did the use of CEEQUAL influence your project?

CEEQUAL took an active role in the direction of the project. It dictated not only a comprehensive list of targets for the team to attain but also helped create a strong and conscientious attitude of consideration to the general principles of the environmental, ecological and social effects of the project throughout the design and construction. The influence of CEEQUAL brought together all staff parties involved with the project in a singular and concentrated effort in order to achieve the sustainability rating.

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

New Low Level Waste Facility

New Low Level Waste Facility

The project involved the Design and Build of two sub-surface vaults for the disposal of solid low-level radioactive waste from ...
E16 Bagn-Bjørgo, Norway

E16 Bagn-Bjørgo, Norway

E16 Bagn–Bjørgo is an 11.1 km stretch of the main road between Norway’s capitol Oslo and the second largest city, ...
Olympic Park: Media Hub Multi-Storey Car Park | CEEQUAL

Olympic Park: Media Hub Multi-Storey Car Park (MSCP)

The design and construction process responded to the high standards for sustainability set out by the Olympic Delivery Authority, achieving ...
Frodsham Wind Farm
| CEEQUAL Case Studies, Energy, UK

Frodsham Wind Farm

Frodsham Wind Farm is one of England’s largest onshore generating stations, and the largest in the Cheshire region, with an ...
Meadow Lane Waterfront Regeneration

Meadow Lane Waterfront Regeneration

Over a five year period there has been quality improvements to the Nottingham Beeston Canal towpath where pedestrian counters and ...
Glenconway Wind Farm
| CEEQUAL Case Studies, Energy, UK

Glenconway Wind Farm

The Glenconway Wind Farm was developed by Gael Force Renewables Ltd, a Joint Venture between McLaughlin & Harvey, Barr and ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags