Balloo Waste Transfer Station and Recycling Centre, Bangor

Balloo Waste Transfer Station and Recycling Centre, Bangor | CEEQUAL

CEEQUAL Very Good – Whole Project Award
Version 3, Aug 2009 | Bangor, Wales

ClientNorth Down Borough Council
Design teamMichael Whitley Architects
Lead ConsultantAlbert Fry Associate EngineersAH Design M&E ConsultantsVB Evans Quantity Surveyors
Main ContractorHeron Brothers Ltd.
Assessor: Mael Wilford

Project Summary

The Waste Transfer Station is a facility comprising 10,000m2 of machine, technology and administrative support space, which will swallow the waste of an entire borough on a weekly basis. After being sorted, compacted and contained, all collected waste is transferred in sealed containers to various recycling agencies and other appropriate destinations. The brief called for the facility to be one of the cleanest and most efficient in Europe. Aptly the only by-product of the building will be distilled water.

Design Philosophy

The facility is located on a brownfield site along Balloo Drive in Bangor, hitherto a lacklustre link between ring roads. Contextually, the size of the scheme is large. Indeed the designers identified the facility’s substantive form as key to the re-stitching of a somewhat frayed piece of urban fabric, believing that its articulated mass will give the locale some much-needed definition and identity. The efficiency of vehicle movement required within, overlaid with pedestrian circulation patterns and site conditions, dictated the form further.

It was seen as important that this facility would have its own architecture – a principle shared and adopted by the client body. The philosophy behind this was that the waste industry has for too long been housed in buildings which are products of utilitarianism at best, or short-termism at worst, and this is reflective of the values that society has placed on waste and its management. Society in the past has perceived the waste management industry as dirty and a fact of life that would be best hidden out of sight and thus out of mind.

The design challenges that perception and asserts that waste management is a high-agenda, clean and modern business-based industry, which should relate on a civic level with society. As a result the new facility is vibrant, boldly intentional in terms of size, shape and colour, and challenges perceptions of the waste industry – by its own staff and the public alike.

Balloo Waste Transfer Station and Recycling Centre, Bangor | CEEQUAL

Balloo Waste Transfer Station and Recycling Centre, Bangor | CEEQUAL

Balloo Waste Transfer Station and Recycling Centre, Bangor | CEEQUAL

Use of Renewable Energy Sources

Beyond the choice of the site, the scheme is designed to be self-sustaining in its day-to-day life. This is realised by use of solar thermal panels for heating, 900m2 of photovoltaic surface generating electricity for all lighting, an 850KW wind turbine for general power to all plant, and a 72,000-litre rainwater-harvesting tank for wash-down facilities.

 

Sustainable Construction

Carbon production during construction was massively reduced by specifying GGBS concrete mixes throughout – ranging from a 36% mix right up to 75% slag content. The site is drained entirely via a Sustainable Drainage System (SuDS) consisting of slow-flow ponds and swales – thereby also rejuvenating a nearby wood and pond landscape.

 

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

BREEAM And CEEQUAL On The Move
| CEEQUAL News

BREEAM & CEEQUAL: On The Move

BREEAM Director, Dr Shamir Ghumra provides insight on how BREEAM and CEEQUAL have helped city and town planners deliver better, ...
Read More
RAF Lossiemouth | CEEQUAL
| CEEQUAL case studies

RAF Lossiemouth – AOS Project

The project is a full refurbishment of all major airside pavement surfaces at RAF Lossiemouth for a new Boeing P8 ...
Read More
Stockholm Extended Metro Arenastaden Plattform | CEEQUAL
| CEEQUAL case studies

Stockholm Extended Metro – Arenastaden

The extension of the Stockholm Metro is vital to make Stockholm a vibrant and accessible city with a sustainable public ...
Read More
Old Colwyn Coastal Defence and Active Travel Scheme | CEEQUAL
| CEEQUAL case studies

Old Colwyn Coastal Defence and Active Travel Scheme

The scheme represented an opportunity to build on the success of previous phases of the Colwyn Bay Waterfront Project with ...
Read More
Viking Link Bicker Fen Access Road | CEEQUAL
| CEEQUAL case studies

Viking Link (Bicker Fen) Access Road

The Viking Link team used CEEQUAL to deliver a sustainability-driven project. They achieved a 30% reduction in kgCO2 equivalent of ...
Read More
Strule SEC – Site Preparation Works
| CEEQUAL case studies

Strule SEC – Site Preparation Works

The purpose of the project was to redevelop the former army barracks at Lisanelly and St Lucia and to provide ...
Read More

Get in touch

Contact us now or call us on 0333 014 7880 if you would like to talk to our team about how CEEQUAL can support you.